fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Inquiry

Inquiry 7 years 4 months ago #11348

  • Anand Kakkar
  • Anand Kakkar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi,
I came across the following question,

Q: PM detects negative variance, what should he do FIRST
initiate a change request
OR
Perform Root cause analysis

My guess is Initiate a change request BUT incase the flaw is in the process, then will it not be good to improve the process first and then request a change

Please advise

thanks

Anand

Inquiry 7 years 4 months ago #11355

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Until the PM knows what change to make (recommend) there is no basis for a change request.

Thus, if those are the only two options, you have to choose doing a root cause analysis.

Best regards,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
The following user(s) said Thank You: Gail Freedman
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login