Project Risk Management Help 7 years 4 months ago #11134

  • Nicholas Ablett
  • Nicholas Ablett's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 7
  • Thank you received: 1
Hello, I am working through the PMBOK and have reached section 11.4.2.2, modelling and simulation. I understand the concept of what they trying to show however, not the math. Using the data they provide and the formula for probability of the mode on a cumulative curve (c-a/b-a) I arrive to 27% instead of 12% as in the PMBOK.

Am I making a mistake with my logic?

Project Risk Management Help 7 years 4 months ago #11280

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 126
  • Karma: 7
  • Thank you received: 25
Nick,

Don't get too far into the weeds here, there won't be any complex math required on the exam involving modeling and simulation. Simply understand the concepts and you will be fine.

- Steven
The following user(s) said Thank You: John Wolverton
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login