TOPIC: Question about change requests

Question about change requests 7 years 5 months ago #10994

  • Jeffrey Ho
  • Jeffrey Ho's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hello everyone,

Quick question about change requests that I'm very confused about.

Do ALL corrective, preventative, and defect repair actions from the PM REQUIRE going through integrated change control process (i.e. need a change request)? (including those that does not impact baseline and impact baselines).

Thanks!

Question about change requests 7 years 5 months ago #11008

  • John Wolverton
  • John Wolverton's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 118
  • Karma: 1
  • Thank you received: 27
Jeffrey
Sorry, too many actions in one question. First, any time you see a question that has ALL inclusive terms - it's just a bad question. The correct answer would be "It depends."
If corrective and defect repair is because of issues within the design then most likely yes a CR is needed. If it's because a work didn't follow the work instructions, then No CR is needed. I would review Pg 353 or the PMBOK Guide. If the question is about contingency and workarounds, yes a CR is needed.
Hope this helps
jfw
John F. Wolverton, PMP®
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login