fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project Charter update

Project Charter update 7 years 6 months ago #10645

  • Haitham
  • Haitham's Avatar Topic Author
  • Visitor
  • Visitor
Hi,
should the project charter be updated ( through perform change integration) once the change occurs to the scope or schedule constrains or risks updated?
or the charter remains as agreed/ signed in the beginning of the project and the update only will occur in the scope baseline or schedule baseline?
and when the Charter will be updated?
Thanks

Project Charter update 7 years 6 months ago #10682

  • ERIC BARTLETT
  • ERIC BARTLETT's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Karma: -1
  • Thank you received: 3
These are really great questions. First, let's make sure you're clearly distinguishing your knowledge areas. The Project Charter is an output of the Develop Project Charter process in the Integration Management knowledge area (initiating process group). Scope Management is it's own knowledge area producing, of course, the scope baseline. Similarly, the schedule baseline is created in the Time Management knowledge area. Both of these baselines are created in the planning process group.

All being said, change requests against the scope and schedule baselines involve internal monitoring, controlling, and executing of the project against those baselines. Changes in the Project Charter, although still requiring approval through the Change Control Board, are often external to the project (i.e., changes to the organization). A very common change may relate to those running the project, both as the sponsor and/or the Project Manager. Other reasons may involve changes to the EEFs/OPAs that are being used as INPUTS to the Develop Project Charter process.

If you consider the list on pg. 72 of the PMBOK (5th ed), any of those high-level items could compel a change w/in the Project Charter. Since this is a formal document of the project, it would require board approvals.
Hope that helps you, but please let me know if it doesn't!

Regards,
Eric Bartlett, PMP
Community Moderator
The following user(s) said Thank You: Haitham M, Florian Emery
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login