fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Uses of Resource calendars in ITTOs

Uses of Resource calendars in ITTOs 7 years 6 months ago #10486

  • Basanta
  • Basanta's Avatar Topic Author
  • Visitor
  • Visitor
Hi, Everyone i am studying ITTOs in PMBOK. I am little confusing on Resource calendars, It is output of Executing process group ( Acquire Project Team & Conduct Procurement) and comes an input to Planning process group( Estimate Activity Resources, Estimate Activity Duration, Develop Schedule, Determine Budget). As i think with out resource calendars we can not complete Estimate Activity Resources, Estimate Activity Duration, Develop Schedule, Determine Budget. But the same is an out put of Acquire Project Team & Conduct Procurement. Is this mean we 1st perform Acquire Project Team & Conduct Procurement process then do Planning like. Estimate Activity Resources, Estimate Activity Duration, Develop Schedule, Determine Budget.

Kindly enlighten little more in this area.

Basanta

Uses of Resource calendars in ITTOs 7 years 6 months ago #10527

  • ERIC BARTLETT
  • ERIC BARTLETT's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Karma: -1
  • Thank you received: 3
Hello Basanta,
I'll do my best to simplify this. First, you can be assured that you're not the first to struggle with this logic. If you search through the PM Prepcast archive, you'll find several folks that have similar questions.
The easiest answer is that you need to consider all processes and process groups as iterative and cyclical. The PMBOK mentions this several times in each chapter, but it's difficult to really capture this in a linear (book) fashion. Here's what helps me: when I see Inputs that are also Outputs in other processes, and vice versa, I immediately understand them as cyclical. This is especially true with Project Documents (such as the Resource Calendar). Simply put, a resource calendar as an output to the Acquire Project Team and Conduct Procurements is pretty obvious (you just added resources), but how do we go backwards and use it as an input to the Schedule/Cost processes?
The answer is that you're only going backwards in the book; the processes are not that sequential. A resource calendar may be very basic at the beginning of a project, but it is consistently updated in any process that adds resources (making it an OUTPUT of that process). As you add or remove resources to your project, all those other processes you cited need to be updated too, so it becomes a very cyclical process. During Estimate Activity Resources, you may update the Resource Calendar but, even more important, define additional Activity Resource Requirements. These additional requirements may then become INPUTS into the Plan Resource Management process , then HRM Plan as an OUTPUT, then the HRM Plan as an INPUT to Acquire Project Team...and we're back where we started.
I hope that helps. As you get better at seeing the relationships of ITTOs from process to process, it becomes easier to pull yourself away from the "Step by Step" approach. Try to think more iteratively and cyclically.

Uses of Resource calendars in ITTOs 7 years 6 months ago #10538

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
Remember that the phases of a project happen simultaneously. So, while you spending a lot of time planning, you'll also do some executing, such as Acquire Project Team & Conduct Procurement. Now, once you complete those executing tasks, you get some outputs like the Resource calendar because you'll know when your personnel are working or on vacation and what your procurements have bought/rented for your project (i.e. bulldozers in a construction projection). Take that calendar to the planning process and use them to continue planning your project timeline. Do you see the connections?
Yours Respectfully
Michael DeCicco, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login