TOPIC: How to know No. of resource (human) on the project.

How to know No. of resource (human) on the project. 7 years 8 months ago #10077

  • Athipol Kruapong
  • Athipol Kruapong's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
I have one question. If I want to know how many people work on my project, where is source I can search for?
1. Human management Plan: Project Organization chart or
2. Human management Plan: staffing management plan.

Please advise me with reason. Thanks.

How to know No. of resource (human) on the project. 7 years 8 months ago #10111

  • Christian Winter
  • Christian Winter's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 5
The project organization chart can be formal or informal depending on the project needs and shows the reporing structure - you may not see all indidual people here, but just teams.
Within the Staffing Management Plan you have the "Resources Calendar" showing when people are available and when they will be used. With this you can determinate when how many people will work in your project (for a specific date, time-range, of whole project duration)

How to know No. of resource (human) on the project. 7 years 8 months ago #10120

  • Athipol
  • Athipol's Avatar
  • Visitor
  • Visitor
Thanks Christian.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login