TOPIC: Risk Quantitative Analysis discussion

Risk Quantitative Analysis discussion 7 years 8 months ago #9949

  • Ha TR
  • Ha TR's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I'm trying to solve this question from HeadFirst Labs book, but I believe the answer the book is saying is incorrect. I think the answer should be a +30.7 and not -30.7, please let me know your thoughts on this:

Prob Imp
35% cost $48 to replace equipment
5% lose $750 in damage costs
15% save $800 in battery costs
10% cost $350 for last-minute rental

What is total EMV? The book says it should be a "-$30.70" and that if you add $30.7 to your budget you will account for risks? I am struggling with this, I think you should not reduce budget at all in this case since in fact you get a saving of $30.7 cumulative EMV of the risks. Let me know your thoughts please.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login