fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project Document updates vs OPA updates

Project Document updates vs OPA updates 7 years 10 months ago #9630

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
When I work on the Exam9 ITTO I found that I've difficulty to answer these kind of question

Example: What is the output of Monitor and Control project work?
A. Project Document update
B. OPA update


Any way I can a better judgement which process output related to EEF, OPA or Prject document update? I cannot memorize these
Thanks
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login