fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Request process priority

Change Request process priority 7 years 10 months ago #9547

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
Hi all

Is their any formal procedure during Change Request?

- Analyse the impact of change
- Issue change request

Which will be done first?
Thanks

Change Request process priority 7 years 10 months ago #9548

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hi Lawrence,
the impact of the change is an important part of the CR document, this implies that you analyze and document the CR impact before issuing it.
Ahmed Amin Abdullah, PMP
Community Moderator

Change Request process priority 7 years 10 months ago #9549

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
Thanks Ahmed

Change Request process priority 7 years 10 months ago #9550

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Lawrence,

A documented change request procedure might look something like below. The procedure for any particular project may be different than this. It really depends on the type and complexity of the project that is being managed.

Mark


Step #1: Identify the need for a change (Any Stakeholder)
Requestor will submit a completed change request form to the project manager
Step #2: Log change in the change request register (Project Manager)
The project manager will maintain a log of all change requests for the duration of the project
Step #3: Conduct an evaluation of the change (Project Manager, Project Team, Requestor) The project manager will conduct an evaluation of the impact of the change to cost, risk, schedule, and scope
Step #4: Submit change request to Change Control Board (CCB) (Project Manager)
The project manager will submit the change request and analysis to the CCB for review
Step #5: Change Control Board decision (CCB)
The CCB will discuss the proposed change and decide whether or not it will be approved based on all submitted information
Step #6: Implement change (Project Manager)
If a change is approved by the CCB, the project manager will update and re-baseline project documentation as necessary as well as ensure any changes are communicated to the team and stakeholders
Mark Wuenscher, PMP
Community Moderator

Change Request process priority 7 years 10 months ago #9566

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
Thanks Mark, the procedure is clear and thanks

Change Request process priority 7 years 9 months ago #9650

  • Senthilkumar Pachai
  • Senthilkumar  Pachai's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 29
  • Thank you received: 3
What about Change Log?

Change Request process priority 7 years 9 months ago #9659

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Senthil,
Not quite sure what you are asking. Yes, you would update the change log as part of the process.
Mark
Mark Wuenscher, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login