fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: change requests & project documents updates

change requests & project documents updates 7 years 10 months ago #9354

  • Housam Krema
  • Housam Krema's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi Everyone,

My Question is regarding to the project documents updates.

In referring to the PMBok Glossary , change request defined as (a formal proposal to modify any document, deliverable, or baseline) , however there are some documents that need to be regularly updated like ( Risk register , Stakeholder register, issue log, Requirement tractability matrix, etc) , my question is : what are the documents included in the above definition?

Thanks
Housam Kerma

change requests & project documents updates 7 years 10 months ago #9356

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
Housam, the documents referred to by the definition means just that: "any document." The definition of the change request is sufficiently general to ensure you understand that when you come across a change request in project management, you'll know to update any document that might be associated with the result of the change request. One example could be resource calendar if a date change for a resource is re-scheduled.
Yours Respectfully
Michael DeCicco, PMP
Community Moderator
The following user(s) said Thank You: Housam Krema

change requests & project documents updates 7 years 10 months ago #9358

  • Stan Po - Admin
  • Stan Po - Admin's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 662
  • Karma: 24
  • Thank you received: 133
Dear Housam,

You are asking an excellent question. We frequently get similar questions from our PM Simulator LiveFeedbackTM feature.

The thing is that the PMBOK® Guide does not really clarify what documents require change request to be issued in order to modify them and what documents do not require it. As you and Michael correctly mentioned, it just says “any document”. But this is not what really happens. Well, the PMBOK® Guide does differentiate between Project Management Plan and Project Documents. Please take a look at the table in the PMBOK® Guide, Fifth Edition, page 78. Project Management Plan (with all its subsidiary plans and baselines) is considered to be a controlled document, while all the rest are non-controlled documents. As a rule of thumb, if a change will require a modification to any of the project management plan documents (controlled documents), then a formal change request should be issued and submitted to the Change Control Board (CCB) approval. However, if the change will affect non-controlled document, for example Issue Log (as a result of some issue that a project manager added), then no change request is required.

Having said that, some cases will require a change request to be submitted even if they touch project documents only. It will heavily depend on the question, on how it’s worded, and what is its context. For example, milestones list is a project document. However, if any milestone is required to be changed, most likely it will require the project schedule (another project document) to be changed, which, in turn, most likely will require a change to the schedule baseline, which is part of the Project Management Plan. And, therefore, a change request will have to be issued.

So, it all depends on the question.

On the flip side, if eventually a change request was issued and approved, project documents are likely to be updated in many cases (you can see that project documents update is one of the outputs from many processes). Again, which document and how it should be updated, will depend on the particular question.

Hope it clarifies.
Regards,
Stan Po, MBA, PMP, PMI-ACP, CSM, CIPP
Product and Program Manager
OSP International LLC
The following user(s) said Thank You: Housam Krema, Abdullah Khan, mavs19

change requests & project documents updates 7 years 10 months ago #9359

  • Housam Krema
  • Housam Krema's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Thanks Stan, very well explained

change requests & project documents updates 7 years 10 months ago #9362

  • Stan Po - Admin
  • Stan Po - Admin's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 662
  • Karma: 24
  • Thank you received: 133
Hi Housam,

You are welcome.

Let me add one more point please: if the Project Management Plan is still being developed (not approved yet), then no change request is required in order to modify the plan or any parts of it.

Good luck in your preparations!
Regards,
Stan Po, MBA, PMP, PMI-ACP, CSM, CIPP
Product and Program Manager
OSP International LLC
The following user(s) said Thank You: Abdullah Khan

change requests & project documents updates 7 years 5 months ago #10966

  • steve
  • steve's Avatar
  • Visitor
  • Visitor
If you disapprove a change request - besides the issues log - what other documents would you have to update?

change requests & project documents updates 7 years 4 months ago #11031

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1
Nice explanation.

However I have one question,

Ideally data flow should be Process-->Raise CR--> Perform Integrated Change control --> Approved CR--> Update Plan.

Then why output of all Control Processes is allays Update project plan and CR?

Should it not be only CR?

change requests & project documents updates 7 years 4 months ago #11032

  • Puneet Maheshwari
  • Puneet Maheshwari's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 26
  • Thank you received: 1

Stan Po, MBA, PMP, PMI-ACP, CSM wrote: Hi Housam,

You are welcome.

Let me add one more point please: if the Project Management Plan is still being developed (not approved yet), then no change request is required in order to modify the plan or any parts of it.

Good luck in your preparations!


Thanks!!

So it this reason control processes have output as Change request as well as Update PMP...?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login