fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Why comes 5.6 Control Quality after 5.5. Validate Scope?

Why comes 5.6 Control Quality after 5.5. Validate Scope? 7 years 10 months ago #9315

  • Marc Rene Woerner
  • Marc Rene Woerner's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 0
Hello,

Don't understand why PMI decided to first talk about 5.5 Validate Scope and then about 5.6 Control Quality in the PMBOK Guide. From a logical perspective, shouldn't these two processes switch their order in the guide? As Andy Crowe also mentioned in his prep book, Validate Scope comes either after Control Quality or it is performed at the same time. So, at 5.5 Validate Scope, the customer is included and accepts (hopefully) the created deliverables but from my point of view an internal 5.6 Control Quality should have taken place before we involve customer.

Can you explain?

Regards,
Marc

Why comes 5.6 Control Quality after 5.5. Validate Scope? 7 years 10 months ago #9319

  • Rahul Kakkar
  • Rahul Kakkar's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 161
  • Karma: 9
  • Thank you received: 56
Hi Marc,

You are right. Actually there’s no “right order” for the Control Scope and Validate Scope processes. Control Scope can happen at any time, because project changes can happen at any time. Validate Scope is usually the last Scope Management process that you’ll do in a project. The trick is that sometimes you’ll find a scope problem while you’re verifying the scope, and you’ll need to do Control Scope and then go back and gather new requirements, rebuild the WBS, etc. So the Control Scope process can happen either before or after Validate Scope.

Hope this helps.
Rahul Kakkar, PMP, MBA
Community Moderator


How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum
The following user(s) said Thank You: Mark Wuenscher, PMP, Marc Rene Woerner
Last edit: by Rahul Kakkar.

Why comes 5.6 Control Quality after 5.5. Validate Scope? 7 years 10 months ago #9322

  • Marc Rene Woerner
  • Marc Rene Woerner's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 0
Thanks Rahul, helps a little. Regards MA
Last edit: by Marc Rene Woerner.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login