fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PROJECT CONFLICT

PROJECT CONFLICT 7 years 11 months ago #9184

  • Henry ILO
  • Henry ILO's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 43
  • Karma: 1
  • Thank you received: 5
Dear all, please which of these is more to cause conflicts / problems on a project? i.e. Communication or Schedule ?

PROJECT CONFLICT 7 years 10 months ago #9323

  • Joseph Feulefack
  • Joseph Feulefack's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Conflict

PROJECT CONFLICT 7 years 10 months ago #9327

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Henry,

Lack of, or poor communication, is more likely to cause conflict in my opinion.

Mark
Mark Wuenscher, PMP
Community Moderator

PROJECT CONFLICT 7 years 10 months ago #9331

  • Bonnie
  • Bonnie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 29
  • Thank you received: 6
This is a good topic for debate, but I think what everyone really wants to know, is what does PMI think?

According to Rita - and most of the internet -

1. Schedules
2. Project Priorities
3. Resources
4. Technical Opinions
5. Administrative Procedures
6. Cost
7. Personalties

PROJECT CONFLICT 7 years 10 months ago #9334

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Here is a good article on the PMI website on communication: www.pmi.org/learning/library/effective-c...ject-management-6480 I haven't read it all the way through yet but it looks interesting.

The reason I say communication is that most of the items in the list go awry and can result in conflict due to poor or ineffective communication and project managers generally spend 90% of their time on communication.

Mark
Mark Wuenscher, PMP
Community Moderator

PROJECT CONFLICT 7 years 10 months ago #9338

  • Stan Po - Admin
  • Stan Po - Admin's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 662
  • Karma: 24
  • Thank you received: 133
This is indeed an interesting topic. However, it's hard to say how the PMI "ranks" difference sources of conflict. All they say is the following: "Conflict is inevitable in a project environment. Sources of conflict include scarce resources, scheduling priorities, and personal work styles." (Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute Inc., 2013, Page 282.)

I think it's pretty in alignment with what Rita Mulcahy is saying in her book, PMP Exam Prep, Eight Edition, 2013. Base on my personal experience, I tend to agree with this order, with only one exception - sometimes personalities with dominated egos will prevail on top of everything else, so you will get a conflict in places and at times where you expect them the least.

As always, an answer to a particular question on the actual PMP exam will strongly depend on the context in which the question is worded. We always recommend that while taking their exam, prospective PMP aspirants will make reasonable assumptions based on all AVAILABLE information in the question and select the BEST answer among the choices given.

Good luck with the preparations!
Regards,
Stan Po, MBA, PMP, PMI-ACP, CSM, CIPP
Product and Program Manager
OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login