fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Questions that ask what a PM should do next

Questions that ask what a PM should do next 8 years 1 week ago #8907

  • Bryan Ostrowski
  • Bryan Ostrowski's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
I had a few questions in the simulator that asked for what the next step should be. One of the answer sets had both 6.1 and 6.2... It was confusing because Define Activities is a part of Plan Schedule Management. For these types of questions, how does a person know if the "general" plan item (5.1, 6.1, 7.1, etc) is the correct choice over the .2 items?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login