TOPIC: Function of the charter

Function of the charter 8 years 1 week ago #8902

  • Lotte Hartmann
  • Lotte Hartmann's Avatar Topic Author
  • Visitor
  • Visitor
Function of charter and content is very well described in PMBok 5ed, but can anybody explain me if charter can be updated in initiating process later in the project lifecycle or if PMI states that charter is never updated, but created when initiating the project?

Function of the charter 8 years 1 week ago #8904

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Lotte,

The project charter is created in the initiating stage and needs to be broad enough so it does not need to be changed as the project evolves. If the project charter is changed, the project sponsor must approve those changes. Depending on the changes, it may also be necessary to revisit parts of the project management plan. For example, if something about the overall objective needs to be changed then it would be necessary to reevaluate the project plan in light of those changes. Hope this helps.

Mark
Mark Wuenscher, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login