fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Questions about L06.99 Self-Assessment for Module 06

Questions about L06.99 Self-Assessment for Module 06 8 years 1 month ago #8484

  • Kelly Coughlin
  • Kelly Coughlin's Avatar Topic Author
  • Visitor
  • Visitor
For L06.99 Self-Assessment for Module 06, Question #8, a scenario is given to figure out the expected activity duration using PERT. How do you know whether to choose Triangular Distribution or Beta Distribution in this case? I chose Triangular and got it wrong. I'd like to know why Beta is correct. Thanks.

Questions about L06.99 Self-Assessment for Module 06 8 years 1 month ago #8661

  • Christian Winter
  • Christian Winter's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 5
In case the estimates were made with no real experience and are more best guesses use the triangular. But when there is already experience from similar previous projects or experts are doing the estimates you should use the beta distribution . Is there such information in the question about the "quality" of the estimates?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login