fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: lead and lag

lead and lag 8 years 3 months ago #8038

  • Hazem Ibrahim
  • Hazem Ibrahim's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 58
  • Thank you received: 2
Is it not more logic and make more sense to describe the FS relationship with a lead 30 days for example to be considered SS relationship with a lag 6 weeks for example .?what is the meaning to say its FS meanwhile it starts before the predecessor process finish actually?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login