fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Risk Management

Risk Management 8 years 3 months ago #8018

  • Gunaseelan Shanmugam
  • Gunaseelan Shanmugam's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 2
This is a question from RITA book . I have a confusion in this . Can you please clear ??

A System development project is near project closing when a previously unidentified risk is discovered . This could potentially affect the project’s overall ability to deliver . What should be done NEXT ??

A. Alert the Project Sponsor of potential impacts to cost, scope or schedule
B. Qualify the Risk
C. Mitigate the Risk by developing a Risk Response Plan
D. Develop a Workaround

I thought the Answer is D since this is an unidentified Risk , but the answer is B .
Is there a need to Qualify the unidentified Risks before developing a Workaround ??

Risk Management 8 years 3 months ago #8031

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
as a general rule, whenever a risk is identified you have to qualify the risk(assess the priority of the risk), then quantify the risk (numeric analysis of the impact) and only after that you need to work on a risk response plan (options to enhance opportunities and reduce threats).

In real life, all steps can take place in the same time.
Ahmed Amin Abdullah, PMP
Community Moderator
The following user(s) said Thank You: Gunaseelan Shanmugam
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login