fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PDM Problem

PDM Problem 8 years 3 months ago #7917

  • Satya Sitharam Nandiraju
  • Satya Sitharam Nandiraju's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 18
  • Thank you received: 2
Please answer the below question
1. Activity A has FF relation with Activity B. A has a duration of 10 days. B has a duration of 9 days with 3 days lag. What is the total duration of A & B?

My answer is 13 days..but author says 12 days

PDM Problem 8 years 3 months ago #7924

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Satya,
When you post questions like this on the forum we ask that you please post the source of the question as well. Where did you find this question?
Thanks,
Mark

P.S. I agree with the 12 days answer. Process A starts on day 1 and ends on day 10. Process B starts on day 4 (3 day lag) and lasts for 9 days, ending on day 12. It is a FF relationship and the total duration is 12 days. I think that is correct.
Mark Wuenscher, PMP
Community Moderator
Last edit: by Mark Wuenscher, PMP.

PDM Problem 8 years 3 months ago #7930

  • Satya Sitharam Nandiraju
  • Satya Sitharam Nandiraju's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 18
  • Thank you received: 2
Thanks Wuenscher

Source is Passionatepmp question pool.

If it is FF with 3 days lag means B has to finish 3 days after A finishes...Is my understanding correct? How could activity B associated with starting of Activity A as it's FF?

PDM Problem 8 years 3 months ago #7935

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Satya,

I have been looking at this a bit more and I think you are actually correct. Actiivity A has a duration of 10 days and we need to count 3 days "lag" beyond day 10 which takes us through day 13. We count back 9 days from that to determine when activity B started which would be at the beginning of day 5. Total duration for A and B would then be 13 days as you stated. I had to remember that for a FF+3 relationship means that activity B finishes 3 days after activity A. My apology for any confusion as earlier, I had put the lag from the start of activity B and it needs to be added to the finish of activity A.

Was there any kind of Gantt chart or network diagram shown with the answer?

Thanks,

Mark
Mark Wuenscher, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login