fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Risk mgmt - Why do Decision tree technique is been part of Perform Quantitative risk analysis?

Risk mgmt - Why do Decision tree technique is been part of Perform Quantitative risk analysis? 8 years 5 months ago #7472

  • Gunaseelan Shanmugam
  • Gunaseelan Shanmugam's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 2
Since Decision tree deals with making decisions, Should it be part of control risk process, which deals with implementation of risk response?

Risk mgmt - Why do Decision tree technique is been part of Perform Quantitative risk analysis? 8 years 5 months ago #7524

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
decision trees is already used in Quantitative risk analysis, and as you suggested during Control Risks we will have to go through the outputs from the Quantitative Risk analysis which will require modification and updates based on the current situation. So, decision trees may be implicitly used during Control risks process.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login