fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Compress the schedule

Compress the schedule 8 years 7 months ago #7318

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 44
  • Thank you received: 1
Hello everybody,

Good evening

I want to ask, If the activity duration estimate has been received What should be done next?

I answer it " Finalize the schedule "

The another option is " compress the schedule "

I wait your reply as soon as possible

Regards.

Moahmmed

Compress the schedule 8 years 7 months ago #7328

  • Jeremy Papp
  • Jeremy Papp's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 4
  • Thank you received: 10
Hi Mohammed,

There is very little context provided in your question. In short, the answer could be either option depending on the situation. Would you provide the full question and its source?

Jeremy
The following user(s) said Thank You: Mohammed Almohimeed

Compress the schedule 8 years 7 months ago #7329

  • Mohammed Almohimeed
  • Mohammed Almohimeed's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 44
  • Thank you received: 1
Hello Jeremy Papp

Thanks for Fast replay:

The question in the attachment file. from Rita Fast track
Attachments:

Compress the schedule 8 years 7 months ago #7339

  • Jeremy Papp
  • Jeremy Papp's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 4
  • Thank you received: 10
Well there are two answers that seem incorrect right away.
Create an activity list -> The question implies we already have an activity list which is a per-requisite for the precedence diagramming method.
Begin the WBS -> We already have the WBS according to the question.

This leaves:
Finalize the schedule
Compress the schedule

I don't think we can 'finalize the schedule' because the sequencing has been done but there is no way to know how long each sequence will take given we only just got the activity durations.

This leaves 'Compress the schedule'. After applying the activity durations, schedule compression will help determine the ideal project duration which comes before we can finalize the schedule.
The following user(s) said Thank You: Mohammed Almohimeed
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login