Hi everyone,
As promised i give you the answer now

This was the 16th question of the integration part in Andy Crowe's book.
The right answer was C, and i did choose B i did exactly like Michael did for almost the same reason.
Here is what the book says :
Prioritizing the changes is the job of the project manager. "A" is wrong because you do not want to distract the team at this point - they should be doing the work. "B" is wrong because it is the project manager to help prioritize competing demands. D is incorrect, because changes cannot automatically be denied simply because you are in execution. ( page 81 )
The Book e even says page 49 in the philosophy of integration management.
" You do not want to call a meeting during the execution every time a problem arises. Instead, the project manager should make decisions and keep the team focused on executing the work packages."
You will not have to erase your message finally Cornelius