TOPIC: stakeholder

stakeholder 8 years 10 months ago #6750

  • Mohit Saxena
  • Mohit Saxena's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hello,
I have a question -
Competitor is a stakeholder or not?
Pls explain why?

Thanks!

stakeholder 8 years 10 months ago #6753

  • Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL
  • Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Karma: 3
  • Thank you received: 14
Hi Mohit,

"A stakeholder is an individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project. Stakeholders may be actively involved in the project or have interests that may be positively or negatively affected by the performance or completion of the project. Different stakeholders may have competing expectations that might create conflicts within the project. Stakeholders may also exert influence over the project, its deliverables, and the project team in order to achieve a set of outcomes that satisfy strategic business objectives or other needs"
The above statement is from the PMBOK (page 30) and it goes on to explain who is a stakeholder and does he relate with the project.
Competitor is not stakeholder because he does not play any role in the success or failure of your project. He may not be even aware of your project. He is external to your project.

Best regards.
The following user(s) said Thank You: Christopher Cunningham

stakeholder 8 years 10 months ago #6754

  • Krishna
  • Krishna's Avatar
  • Visitor
  • Visitor
Stakeholder is somebody who wishes the project to be success.there may be negative staekholders but ultimately after the project is live it would be beneficial for them too.For competitior it would not be beneficial.Infact success of a project is threat for him

stakeholder 8 years 10 months ago #6756

  • Mohit Saxena
  • Mohit Saxena's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Thanks Lazard.
Well explained.

Regards!!!

stakeholder 8 years 10 months ago #6759

  • Tracey South
  • Tracey South's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 131
  • Karma: 6
  • Thank you received: 27
I will also add that while a Competitor is not a stakeholder they often need to be considered when assessing Risks to your project.

Tracey
Community Moderator

stakeholder 8 years 10 months ago #6767

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Totally agree with Tracy, competitors are not stakeholders but the risks that can result from the completion must be considered in the risk planning and management.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login