Which process includes implementation of risk responses? 8 years 11 months ago #6581

  • David Kornaros
  • David Kornaros's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Thank you received: 0
The PMBOK guide (p 349) reads “control risks is the process of implementing risk response plans, tracking…..”
However, PMPrepcast L11.06 (Control risks) says “Risk responses don’t stay in risk mgmt. We don’t actually execute responses here. That happens in the executing processes.”
These statements seem to be in conflict IMO. The PMBOK guide says that risk responses are implemented as part of Control Risks, but Cornelius implies the opposite.

Would appreciate clarity if I'm misunderstanding.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login