I was instructed by PMPrepcast support to post my question here.
I think the PrepCAST Self assessment L02.99 had this answer wrong. Please advise. I welcome input.
Question 15: Complex projects are usually divided into multiple project phases in order to gain more control over the project and to attain the desired results. When project scope is not well-defined and progressively elaborated, which of the following phase-to-phase relationships is best suited for successful project completion?
A.) A Sequential Relationship
B.) An Iterative Relationship
C.) An Overlapping Relationship
D.) Phase-to-Phase relationship has no association with Progressive Elaboration.
Correct answer is B
Explanation: An Iterative Relationship is used where only one phase is planned at any given time. This usually results when a high-level vision is developed for the overall undertaking or project, but the detailed scope is elaborated only one iteration at a time.
Here is my case for why answer B is incorrect and D is correct: the phrase “iterative relationship” does not exist in the PMBOK guide. “Iterative Life Cycle” does. However, the question is asking for a “phase-to-phase relationship”, not a life cycle. And “iterative life cycle” is not a possible answer. Additionally, progressive elaboration is only mentioned in the PMBOK guide in relation to life cycles, not phase to phase relationships, which IMO, would make answer D the correct answer.