Praveen Chandra wrote: The question below is taken from: PM Study Circle questions by M Fahad Usmani
You make a contingency plan for a negative risk, and assign it to a risk owner. What kind of risk response strategy is this?
(a) Transfer
(b) Avoid
(c) Mitigation
(d) Accept
The answer provided doesn't match as per my logic.
I chose D - Accept. However answer provided was C.
Please drop in your views.
Hi Praveen,
Risk mitigation is a risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk, whereas, risk acceptance is a risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Here we are
taking action by creating a contingency
plan and hence the answer is C.
Accepting a risk can either be passive or active. Passive acceptance requires no action except to document the strategy, leaving the project team to deal with the risks as they occur, and to periodically review the threat to ensure that it does not change significantly. The most common active acceptance strategy is to establish a contingency
reserve, including amounts of time, money, or resources to handle the risks. So if instead of creating a contingency
plan and assigning it to a risk owner, we only created a contingency
reserve, the answer in that case would have been D.
Hope this helps.