TOPIC: Clarification on a question - Integration mgmt

Clarification on a question - Integration mgmt 9 years 3 months ago #5968

  • Praveen Chandra
  • Praveen Chandra's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 1
Source - PMP Exam Prep by Rita Mulcahy - 8th edition
Chapter 4 - Integration Management

The question seems very simple, but i am slightly confused:

All technical work is completed on the project. Which of the following remains to be done?

A. Validate Scope
B. Plan Risk Responses
C. Create a staffing management plan
D. Complete lessons learnt

Options B and C are ruled out immediately.
Between A and D - I chose A and it is incorrect as per the book.
My logic was after all technical work is completed, we need to get the scope validated in order to deliver to customer.
However the book mentions correct answer to be D.
Requesting clarification from someone to understand as to how the project is in closing phase?

Clarification on a question - Integration mgmt 9 years 3 months ago #5971

  • Puneet
  • Puneet's Avatar
  • Visitor
  • Visitor
Two choices are close, A and D.

Deliverable are not completed until they are accepted by Customer.

Validate Scope(A) is incorrect because if customer has not accepted a deliverable then it implies that work is not completed. It may require evaluation, identify options to correct the work and then as needed issue change request. Validate Scope is performed for each deliverable moment a deliverable is completed and good Project manager must obtain acceptance from customer as the deliverable is completed. Please note that if there are 100 deliverable then PM must take acceptance from customer during Validate Scope.

Close Project will collect these 100 acceptances from customer and request a formal acceptance of Project Scope. Questions would have more confusing if an option is: Measure Project Scope, which is done before Lessons Learnt.

Even if the question says Project Work, answer will be D again. Project work can contain documents,reports etc which are all deliverable.

Regards,
Puneet
Dubai, UAE

Clarification on a question - Integration mgmt 9 years 3 months ago #5972

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
I Agree with Puneet, completion of work means accepted by the customer so Validate scope has been done already. the next step is to discuss and document the lessons learnt. choice D is the correct answer.

however I think in the real exam, the questions will identify the project state clearer than in the below question.
Ahmed Amin Abdullah, PMP
Community Moderator

Clarification on a question - Integration mgmt 9 years 3 months ago #5974

  • Dawn Upperman
  • Dawn Upperman's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 116
  • Karma: 4
  • Thank you received: 19
Hi Praveen,

I agree with Puneet as well. I also agree with Ahmed's comment that in the real exam, the questions will be clearer than in the this question.

Clarification on a question - Integration mgmt 9 years 3 months ago #5975

  • Praveen Chandra
  • Praveen Chandra's Avatar
  • Visitor
  • Visitor
Thank You Puneet, Ahmed and Dawn.
Appreciate your responses which helped me to get the clarification.

Praveen Chandra
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login