fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Basic question on Approving changes

Basic question on Approving changes 9 years 8 months ago #5245

  • Sagar
  • Sagar's Avatar Topic Author
  • Visitor
  • Visitor
Team,

Recently i went through the sample Q&A where I failed to understand the answers provided by them. Can anyone help to understand the below. Here you go :

Who can approve of changes to any of the primary constraints on your project such as
scope, budget or timeline?

1. The CCB
2. The sponsor
3. Senior management
4. Key stakeholders,

And the answer is 3.

Why not CCB or the sponsor or key stakeholders.?

Basic question on Approving changes 9 years 8 months ago #5246

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hi Sagar,

please let's know the source of this question.

Regarding the answer, I agree with you the CCB is the correct answer.
Ahmed Amin Abdullah, PMP
Community Moderator

Basic question on Approving changes 9 years 8 months ago #5247

  • Sagar
  • Sagar's Avatar Topic Author
  • Visitor
  • Visitor
Thanks Amin for your quick reply. I took this from Edwel PMP bootcamp book.

Basic question on Approving changes 9 years 8 months ago #5249

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
You're right Sagar. This is a basic question, but I think it goes deeper than project change management. Let's try to understand the question further by going to the introduction of PMBOK. I think the question wants you think strategically as opposed to the tactical level of project management execution. Let me explain

We are being asked to change constraints.

In the PMBOK 5th Edition, p.5, balancing constraints [which are often imposed through the business case analysis and subsequent approved charter] include scope, quality schedule, budget, and resources. Affecting one affects others and more than likely the project you are working on is not the only one in your organzation. It might be, but large organizations have Program Management Offices to oversee the distribution of these necessities. Often these necessities are what senior management authorizes because they can't have well-meaning project managers deciding to change timelines and budgets at whim. That not only spells trouble for you as a project manager, but impacts the senior management's resourcing of its strategic initiatives.

So if your project has a constraint in total time or funding allotted, you should expect to bring this to the attention of the sponsor who may simply be your office manager or one level up and would not be someone who can decide on re-allocated resources to your project without some form of approval from senior managers.
Yours Respectfully
Michael DeCicco, PMP
Community Moderator

Basic question on Approving changes 9 years 8 months ago #5252

  • Batool Morales
  • Batool Morales's Avatar Topic Author
  • Visitor
  • Visitor
So Michael should we always think that any contraint changes must be approved by Senior managements ?
Thanks

Basic question on Approving changes 9 years 8 months ago #5254

  • Sagar
  • Sagar's Avatar Topic Author
  • Visitor
  • Visitor
Thanks micheal for your explanation.

Basic question on Approving changes 9 years 8 months ago #5264

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 49
  • Thank you received: 11
Sagar,

I agree with Ahmed, that the CCB should be the correct answer. The CCB controls your project's baselines (such as scope, budget, and schedule).


However, I think I can understand why whoever wrote that question said the answer is 3. For massive, fundamental changes to a project, additional leadership buy-in is typically required. If management kicks off a project to accomplish X, and then later your CCB decides to only accomplish X/10 (without consulting senior management), you're going to have problems!
Steve Sandoval, PMP
Community Moderator
Last edit: by Steve Sandoval. Reason: typos

Basic question on Approving changes 9 years 8 months ago #5286

  • Murambwa Clever Haparari
  • Murambwa Clever Haparari's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
But I would think that the CCB could be made up of Sponsor and Senior Management, why would you have Junior Personnel on the CCB. Sponsor or customer may be next level of approval if they have not been part of the CCB.

Guns out for CCB to approve primary constraints changes.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login