fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Quality tools Question

Quality tools Question 9 years 11 months ago #4901

  • James Whelan
  • James Whelan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 2
In the PMBOK there are two set of Quality Tools. 1. the basic seven and 2. Quality Management and Control Tools. Are these used in all three quality processes. I don't see Quality Management and Control Tools mentioned in the Control Quality process. odd since Control tools is in its name. if they are not used, why not?

Quality tools Question 9 years 11 months ago #4904

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 49
  • Thank you received: 11
Hello James --

I would point out that the PMBOK 5th edition section 8.2.2.1 starts with the following sentence:

The Perform Quality Assurance process uses the tools and techniques of the Plan Quality Management and Control Quality processes.


It then goes on to list some "other tools that are available". I would also ask you to review Figure 8-9, which demonstrates the data flow for the Perform Quality Assurance process. This clearly shows that items from Plan Quality Management and measurements from Control Quality are both inputs into Perform Quality Assurance. I believe that it is for this reason that the T&T list names the item as "Quality managment and control tools" -- since the tools of those two processes are basically inputs into this one!

Hopefully this helps to shed some light on the situation.

-Steve
Steve Sandoval, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login