Hi folks,
I am currently studying for the PMP exam. During my studies I encountered similar questions which I don't really understand. Maybe you can help me?

This is just an example to show you which kind of questions I mean. This is not a copy of a published question but just from my memory.
Q: A project has a CPI of 0.94 and a SPI of 1.0. Which statement is true
1. The project was finished on time and under budget
2. The project was finished on time and over budget
3. The project was cancelled before completion and at this time was under budget
4. The project was terminated and was not entirely completed
I do understand the meaning of the CPI and SPI numbers but don't seem to find a logic in these questions.
Is there any structure which I can follow?
Thank you for your help.
Regards
Florian