TOPIC: A Question on Cost of Quality and explanation

A Question on Cost of Quality and explanation 10 years 1 month ago #4685

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
Which of the following is also known as failure costs?


A>Cost of poor quality
B>Internal costs
C>Prevention costs
D>Cost of defects


I need to know the explanation of the answer. The ans as per one of the education provider is : A

My question is why it is not D? Is Defect not a failure? why will the cost of defect will not come under failure cost? Defect will require Rework and that is under failure costs.
IMPOSSIBLE Itself says I M POSSIBLE

A Question on Cost of Quality and explanation 10 years 1 month ago #4686

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Abhirup,

First things first... please follow proper etiquette and give credit . Please tell us who created this question.

Thank you.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

A Question on Cost of Quality and explanation 10 years 1 month ago #4688

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
This question was created by Simplilearn.
IMPOSSIBLE Itself says I M POSSIBLE

A Question on Cost of Quality and explanation 10 years 1 month ago #4692

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hi Abhirup.

This is a PMBOK definition, failure costs are the cost of poor quality; costs spent during and after the project because of failures to meet the requirement.

as for other choices:
>Internal costs : this is a category of failure costs, failures found by the project team.
>Prevention costs : this is part of cost of conformance. investments in preventing non-conformance.
>Cost of defects : this is part of internal costs.

please refer to section 8.1.2.2 Cost of Quality (COQ) in the PMBOK Guide it includes more clarifications.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login