fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Discretionary Dependency in Precedence Diagramming

Discretionary Dependency in Precedence Diagramming 10 years 10 months ago #4013

  • Mehmet Tahir Dede
  • Mehmet Tahir Dede's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Thank you received: 1
Hello,
There is a question on EXAM Simulator 3 Question 146 as
What is Discreationary Dependency in Precedence Diagramming Method?

Answer is A Dependency that is established based on knowledge of best practices which is right but the same question has an option as a dependency that is in the poject team' s control.

I think both answers are right?

Can you please explain why a dependency that is in the project team' s control is the wrong answer?

Discretionary Dependency in Precedence Diagramming 10 years 9 months ago #4014

  • Sachin Vehale
  • Sachin Vehale's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 16
  • Thank you received: 4
Hi - Both answers are right but 'Answer A' is the BEST answer for this question.

Exam might test you to choose the BEST answer , where all answer options might be correct w.r.t. the question asked.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login