fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: risk question in rita's book

risk question in rita's book 11 years 5 months ago #3418

  • Diaa Eldeen Ahmed Abdelghaffar
  • Diaa Eldeen Ahmed Abdelghaffar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Karma: 1
  • Thank you received: 0
i found that question in Rita's book which i could not understand the answer

a project manager has just finished the risk response plan for US$ 387.000 engineering project which of the following should he probably do next?

1- determine the overall risk rating of the project.
2- begin to analyze the risks that show up in the project drawing.
3- add work packages to the project breakdown structure.
4- hold a project risk reassessment

the correct answer as per the book is (3), but i think it is 4

also in general risk's question in this book are very difficult i do not know if it is the same level of exam questions

risk question in rita's book 11 years 5 months ago #3419

  • Ade Ajayi
  • Ade Ajayi's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Sounds like a simple logical case of moving from planning phase to execution phase to me, but yeah Rita does have a mind of her own. Other options sound like taking a step back in the process, same spot or out of the process, what do you think.

risk question in rita's book 11 years 5 months ago #3420

  • James Switzgable
  • James Switzgable's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I sometimes get tripped up by the wording of the question. To me the question is missing a word, either "creating" or "executing" the risk response plan. Depending on that verb, the answer would be either #3 or #4. Also, for #3, it would be better if the answer included an "if needed" since your risk plan will not always require additional work packages to the WBS.

risk question in rita's book 11 years 5 months ago #3421

  • Ade Ajayi
  • Ade Ajayi's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Agree with you James, highlights the fact that understanding the question is as important as knowing or thinking you know the answer. Lots of "probably" questions designed to throw the thought process of track. Lots of questions also do not have a right answer, more like a best answer, and I think this is one of those questions.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login