fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Strange question on practice test about

Strange question on practice test about 11 years 6 months ago #3354

  • Ron Cruz
  • Ron Cruz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 1
Of course it's a free exam so it could very well be wrong but here's the question:

"Which of the following does NOT generate changes to project documents?"

And the answer is Define Activities.

I really don't understand this. I mean the activity list and milestones list are part of the project plan and documents. Am I missing something or is this just a terrible test?

Strange question on practice test about 11 years 6 months ago #3355

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Ron,

Upon initial review I would tend to agree with you. Please tell me that this is not one of our questions... ?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Strange question on practice test about 11 years 6 months ago #3356

  • Ron Cruz
  • Ron Cruz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 1
Not one of yours.
Actually it was what brought me here. I was like "enough of this free crap. I'm going somewhere I know I can trust the questions"

Strange question on practice test about 11 years 6 months ago #3357

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Phew!

Glad to hear it!
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Strange question on practice test about 11 years 6 months ago #3377

  • Srivathsalachary Vangeepuram
  • Srivathsalachary Vangeepuram's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
If a process happens to update other process' outputs, then we would consider it as project document updates.
Per PMBOK4, Define activities generates activity list,attributes and milestones, by taking inputs from scope baseline, PMIS (EEF), scheduling methodology (OPA) etc. The process does not update any existing project documents by that time.

For example, Risk response planning may identify changes to WBS and the activities list. This is another PMIism, may be!

I feel while decomposing the work packages into activities, you might realize that few work packages were missing, and you might as well change WBS. If PMP is not yet approved, thats okay, other wise you would go through change control process to reissue scope baseline.

Just wanted to share my viewpoint!

Regards,
Chary
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login