fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: CPM Calculations - Start with day 0 or day 1?

CPM Calculations - Start with day 0 or day 1? 11 years 6 months ago #3349

  • Abhinav Gupta
  • Abhinav Gupta's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 1
For the exam does it matter whether you start with day 0 or day 1 for your CPM calculations? The book I am referring uses day 0, while the prepcast uses day 1. While float and critical path will remain the same using both methods, the ES & EF dates might differ. I prefer using 0 as the first day as it is not only faster but also reduces the chance of mistakes!

Your thoughts?
The following user(s) said Thank You: Aman Khan

CPM Calculations - Start with day 0 or day 1? 11 years 6 months ago #3353

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
This question has been asked here in the forum about 5 times so far. Here is once again my standard answer, copied from our PMP Exam Formula Study Guide, which you can find at www.pmformulas.com :

There are two approaches for calculating ES, EF, LS and LF:

• First approach: You calculate the network diagram starting on day 0
• Second approach: You calculate the network diagram starting on day 1

In the PMP Exam Formula Study Guide we use the second approach, because when your sponsor tells you that your project starts on the first day of September, then that is September 1, not September 0. This is also the way that all modern scheduling tools seem to work. You schedule your project based on a calendar start date and not "on day 0".

That is why there is a slight difference between the calculations: you have to add/subtract 1 from the results in the second approach.
Of course, this often leads to confusion for PMP exam students and they ask which formula should we use on the exam?

We have discussed this with a number of PMP trainer colleagues and they agree that PMI does not "support" a specific method of calculating a network diagram. (Remember that next to the two options shown above you could also calculate a network path starting on a specific calendar date in hours instead of days, making the calculations even more complex).

Neelesh Pandey, PMP (a PMP trainer) has told us the following about his teaching experience with these formulas:

I use a PowerPoint presentation with animations to prove that no matter what method you follow, the result is same. I choose a part of a network diagram with four sequential activities, which sum up to a duration of 10. This path has a float of two based which we calculate LS and LF. My participants once assured that it doesn't make a difference tend to use the "zero" method. Somehow they find it simple as no subtraction is needed. PPT animation helps me a lot and also I ask my participants to calculate ES, LS, EF, and LF for a simple network diagram using both the methods.

As you see, both of these calculations will lead to the correct answer. However, in the exam the big difference is that the first approach (starting on day 0) involves fewer calculations because you don't have to "+1 or -1" each time. So, in order to reduce your "risk" of doing a calculation wrong and saving time during the exam, you might want to initiate the network diagram with day 0. However, in "real life" starting with day 1 is more appropriate.

Since PMI is aware of these varying methods, you should not see a question on the exam where only the application of one or the other leads to the correct answer.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Abhinav Gupta, Kay William Schmitz, Jibril Babatunde

CPM Calculations - Start with day 0 or day 1? 11 years 6 months ago #3361

  • Abhinav Gupta
  • Abhinav Gupta's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 1
Hi Cornelius, I read this post in your voice :P

Unfortunately, this does not answer my question regarding the ES & LS dates. Using either technique, it is clear that the float values will be the same. However, if you use the day 0 method, the ES & LS dates are different from the ES & LS dates obtained using the day 1 method. I have found that you have to add 1 to the ES & LS dates in the day 0 method, you get the same dates as those in the day 1 method.

While PMI does not prefer any particular technique, what do you do if a question on the exam asks "What is the ES of activity D"? Clearly there would be two possible answers for this question.

CPM Calculations - Start with day 0 or day 1? 11 years 6 months ago #3367

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Abhinav,

If PMI had such a question on the exam (which I strongly doubt) then they would make sure that there could be "no" discussion about the answer. So let's say that the ES your activity D is on day 4 or day 5 (depending on which method you used to do the forward/backward pass). Then PMI would give you the following options to select from:

A.) Day 1
B.) Day 4
C.) Day 8
D.) Day 12

As you can see the answers are far enough apart so that B is the only "logical" answer.

And this is exactly my point: PMI will probably not have such a question on the exam because depending on the approach you choose you get a different answer. They know about this. They will avoid this, because they don't want students to come back again and again about this question contesting it.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last edit: by Cornelius Fichtner.

CPM Calculations - Start with day 0 or day 1? 11 years 6 months ago #3369

  • Abhinav Gupta
  • Abhinav Gupta's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 1
Aah that makes sense. Thanks a lot for clarifying Cornelius.

Until next time! :)

CPM Calculations - Start with day 0 or day 1? 7 years 10 months ago #9510

  • svet
  • svet's Avatar
  • Visitor
  • Visitor
if you calculate feee float there will be difference in +-1 depending on the method chosen

CPM Calculations - Start with day 0 or day 1? 5 years 9 months ago #16446

  • Elizabeth Hibbert
  • Elizabeth Hibbert's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Karma: 1
  • Thank you received: 2
Thanks all! Why have a question on the prep exam where the options are only 1 day apart if the PMP exam will not do that?
The following user(s) said Thank You: Janet

CPM Calculations - Start with day 0 or day 1? 5 years 2 months ago #18464

  • Miguel Sifontes
  • Miguel Sifontes's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I just bought the PMP Simulator and I found in PMP Exam 1 question 42, exactly this situation. My answer was 2, based on Zero criteria, but the Simulator´s answer is 3 based on 1 Criteria. So actually you can find this kind of questions on the real exam , can´t you? Am I mistaken about this statement?. For Float calculation you can get the same result using either method, but what about activity duration?

CPM Calculations - Start with day 0 or day 1? 4 years 1 month ago #23721

  • Lata Chauhan
  • Lata Chauhan's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
I have same doubt on questioID 614006 from PMP simulator. Duration estimates, what is the difference in calculation when questions says, activity starts on day 1.

CPM Calculations - Start with day 0 or day 1? 4 years 1 month ago #23731

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Lata,

depending on the method you use, the only difference you will get is in the start and end dates of activities, and the way you compute them (for both the forward and the backward pass), but the activity duration remains the same—regardless of the method you follow.

For example, if activity starts on Day 1, you will compute EF = ES + duration - 1; if activity starts on Day 0, EF = ES + duration.

Hope this helps,

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login