fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EVM question

EVM question 11 years 8 months ago #3169

  • Konstantinos Limas
  • Konstantinos Limas's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 5
This is a question from PMStudy.com free test.

Question No : 165

You are working on a 12 month assignment to build a website with 4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3 months. After 6 months, you determine that only $ 400,000 of work is completed and cost incurred is $ 800,000. What is the ETC?


Choice 1 $ 2,000,000

Choice 2 $ 1,500,000

Choice 3 $ 1,000,000

Choice 4 1,200,000


Any thoughts?

EVM question 11 years 8 months ago #3174

  • Cathy Schloeder
  • Cathy Schloeder's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
$1.2M (4th answer). Calculate the EAC which is 2M and subtract actual cost $800K and you get $1.2M. Good luck.

EVM question 11 years 8 months ago #3187

  • Fadi Sodah
  • Fadi Sodah's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
EAC= AC + (BAC-EV)/CPI = $800,000 + ($ 1,000,000 - $ 400,000)/($ 400,000 / $ 800,000) = $ 800,000 + ($ 600,000/0.5) = $ 2,000,000
ETC = EAC – AC = $ 2,000,000 - $ 800,000 = $ 1,200,000

EVM question 11 years 8 months ago #3207

  • Visalakshmi Korrapolu
  • Visalakshmi Korrapolu's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
Another way is to directly use (BAC-EV)/CPI without calculating EAC - where Actual Cost is added first and then subtracted.
The following user(s) said Thank You: DINESH SHANMUGAM
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login