fbpx

Reply: Risk register updates

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Risk register updates

Max. showing the last 6 posts - (Last post first)
13 years 7 months ago #2449

Ankou Kohlee

Ankou  Kohlee's Avatar

Hi,

In Identify Risk process of the Risk Management knowledge area, the risk categories are updated in the Risk Register (as an output). Risk categories are created in the Plan Risk Management process and updated in Identify Risks. I believe Risk Categories are updated as needed through out the Risk Management knowledge area.

Hope this helps. :)
13 years 7 months ago #2440

Kerri Karel

Kerri Karel's Avatar

Are we to assume that risk categories are not included in the Risk Register output of Identify Risks but are in the Risk Register updates of Perform Qualitative Risk Analysis?:blink:

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login