TOPIC: Project Standard Deviation

Project Standard Deviation 13 years 3 months ago #2341

  • Adam Leslie
  • Adam Leslie's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 3
Has anyone seen any sample questions that deal with calculating the PROJECT STANDARD DEVIATION?

After you calculate EAD (PERT), activity standard deviation & activity variance for each activity in the critical path my understanding is the following:

1. You add your EAD's (PERT) to calculate PROJECT DURATION
2. You add your activity variances to calculate PROJECT VARIANCE
3. You take the square root of the PROJECT VARIANCE to obtain the PROJECT STANDARD DEVIATION
Regards,

Adam
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login