fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PMP Exam calc of ES, EF, LS, LF, Float.

PMP Exam calc of ES, EF, LS, LF, Float. 13 years 4 months ago #2232

  • Tarek Al-Fahham
  • Tarek Al-Fahham's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 71
  • Karma: 3
  • Thank you received: 0
Based on PM PrepCast and Formula Study Guide, here are the fomulas:

EF = ES + Dur - 1
ES = EF of prev (largest) + 1
LF = LS of succ (smallest) - 1
LS = LF - Dur + 1
Float = LS - ES = LF - EF

However, it was mentioned that there are other calculation methods, which where the Start Day is Zero.

I have searched and found this:

www.projectlearning.net/pdf/X2_1.pdf

As we can see from the PDF, the formulas are similar, but they start at Day Zero, and there is no +1 nor -1.

What is expected on PMP Exam ? Does it make any difference ?

Tarek.

Re:PMP Exam calc of ES, EF, LS, LF, Float. 13 years 4 months ago #2233

  • Adam Leslie
  • Adam Leslie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 3
Both methods give the same result. No difference between the two, and the exam does not care.
Regards,

Adam

Re:PMP Exam calc of ES, EF, LS, LF, Float. 13 years 4 months ago #2234

  • Tarek Al-Fahham
  • Tarek Al-Fahham's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 71
  • Karma: 3
  • Thank you received: 0
There will be difference if in exam required to calculate say, LF of a given activity on the Network Diagram.

But, there will be no differece to calculate Total Float and Find the Cretical Path.

Tarek.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login