fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: project selection method

project selection method 15 years 4 months ago #214

  • Francisco Monterrubio
  • Francisco  Monterrubio's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi , could you give an explanation of benefit measurement project selection method and constrain optimization project selection method.

Thanks in advance

Re:project selection method 15 years 4 months ago #232

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1997
  • Karma: 121
  • Thank you received: 618
Hello Francisco,

The "Benefit Measurement Method" and the "Constrained Optimization Method" are both project selection methods.

However: Project selection methods have been removed from the PMBOK Guide 4th Edition. Because of this you can safely assume that they are no longer on the PMP exam and you do not need to know these two methods in detail. As long as you understand that these two terms are project selection methods you will be fine (in fact... you are over-prepared).

But to answer your question:

Benefit Measurement is a comparative approach and examples would be scoring models, cost-benefit analysis, review board, economic models. Benefit measurement is the most common approach.

Constrained Optimization is a mathematical approach and examples would be linear programming, nonlinear programming, integer programming, dynamic programming, multi-objective programming. Constrained optimization makes use of math models and complex criteria and is often managed as a distinct project phase.

But remember: You should not need this knowledge any longer. The new PMBOK Guide discusses project selection on a high level (see chapter 2) and doesn't go much more into specifics other than saying that "every project should support your company's strategic plan".
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:project selection method 15 years 4 months ago #233

  • Francisco Monterrubio
  • Francisco  Monterrubio's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
thanks ,I'm working very hard once again thanks
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login