TOPIC: Activity Duration Equation + email Cost Estimating

Activity Duration Equation + email Cost Estimating 13 years 5 months ago #2138

  • Saad Al Naib
  • Saad Al Naib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Dear Sir,

I have two questions:

1- Equations of Network Diagram in specific:

- Activity Duration = EF-ES+1
- Activity Duration = LF-LS+1
- ES = EF of predecessor +1
- LF = LS of successor -1

Only you and PMP Headfirst explained that approach.

To understand, I pulled on solved network problem and want to see above true in some books right, others not showing that am talking about +1, -1 of the above equations. Why?

Ex. Page 90 of PMP Certification Mathematics by Vidya And Riva

9 2 11 ES Dur. EF
D Task name
19 10 21 LS Slack LF


2- Just received audio version of your postcast Cost Budgeting

hw.libsyn.com/p/5/a/3/5a3116d9237f4a9d/P...l_eid=&l_mid=1788367

Is this different from your video prepcast and where we find all audio links?

Thank You.

saad

:Activity Duration Equation Question 13 years 4 months ago #2139

  • Saad Al Naib
  • Saad Al Naib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Hi,

I have only one questions:

Equations of Network Diagram in specific:

- Activity Duration = EF-ES+1
- Activity Duration = LF-LS+1
- ES = EF of predecessor +1
- LF = LS of successor -1

Ex. Page 90 of PMP Certification Mathematics by Vidya And Riva

9 2 11 15 1 16
D F
19 10 21 21 6 22

ES Dur. EF
Task name
LS Slack LF

Why other diagrams in other books like above won't get right answer or am I missing something.

email Budget question before understood.

Thank You.

saad
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login