I too, originally thought the answer was D, and not A. I eventually realized that it is indeed A.
Here’s why:
Every project that completes will ALWAYS have an SPI of “1”. That is indicating that the work actually accomplished (EV) and the work originally planned(PV) are the SAME. In other words, all the work has been accomplished, so the project is complete. (Note: this has NOTHING TO DO with the CALENDAR, or whether or not the project finished on the scheduled/contracted date. That’s where we easily get confused.)
DURING a project, you can look at the SPI and make correlations with “running ahead or behind” schedule…. but that SPI number is always on a countdown to becoming exactly “1”. No more, no less. So AFTER a project, your SPI is “1”.
So at post-mortem, if the SPI in your report reads “greater than one”… it means only one of two things:
1) the project was terminated, at a point in time when you just happened to be ahead of schedule, so the SPI in the report shows that fact; –OR--
2) You literally finished the entire project ahead of schedule, closed out the project early, and in your final report listed the SPI that was current on the day you completed work, rather than correctly calculating the SPI as of the CONTRACTED (planned) completion date. If you had indeed waited until the scheduled/planned finish-date to do your final calculations, on THAT particular day, the day your project was contractually completed, your SPI would read exactly “1”.
Since scenario #2 above involves someone erroneously recording the wrong numbers in their final report, that leaves only scenario #1, which in Oliver Lehmann’s practice question, would be option A.
PS: In one of the posts above, Amit Jain gives an example of painting walls and finishing early. That is exactly the case I am describing in Situation #2 above… which is why I originally argued that the answer was choice “D”. Until I thought it through. On the day Amit painted that last wall, his SPI would be greater than one. One the day he was scheduled to be finished painting all the walls, his SPI would be “1”.
PPS: The term “post-mortem analysis” in PMP world means only that it is after the project has closed… it does not mean that the project was killed.