fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Please answer & explain ...

Please answer & explain ... 14 years 1 week ago #1686

  • SAMIK RAHA
  • SAMIK RAHA's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hello Mr. Fichtner,
First I would take this opportunity to thank you for the PM PrepCast. It's indeed a great help.
I am preparing for the PMP Certification this year end. In the preparation process I came across a question as under - I did not fully agree to the explanation provided in the source and as such would ask your opinion on the same.
You are a project manager for a large consulting firm. Your superior has just asked for your input on a decision about which project your company should pursue. Project A has an internal rate of return (IRR) of 12 percent. Project B has a predicted benefit cost ratio (BCR) of 1.3. Project C has an opportunity cost of U.S. $75,000. Project D has a payback period of six months. If you had to choose based on this data,which project would you select?
A. Project A
B. Project B
C. Project C
D. Project D

Regards,
Sam

Re:Please answer & explain ... 14 years 1 week ago #1687

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Hello Samik,

Please provide the source where you found this question and their explanation in regards to which of the questions is correct.

I'll then take a look at it.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Please answer & explain ... 14 years 1 week ago #1689

  • SAMIK RAHA
  • SAMIK RAHA's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hello Mr Fichtner,

I found it in one practice questions in a book by Rita Mulcahy.

Answer A
Explanation This is a question about project selection and could easily be included in other chapters. In order to interpret the information, you need to know what each item is. The benefit cost ratio for choice B is unfavorable. There is not enough information provided to support recommending or not recommending choices C or D. This leaves only choice A, with a 12 percent return, as providing a clear benefit.

My point is - I do not disagree that A is correct but I cannot agree that B is incorrect. I have highlighted the portion which says "BCR is unfavorable". To my understanding any BCR above 1 should be favorable. Based on that I had chosen B. To me A was incorrect as I was thinking that BCR should be a more easier & reliable in such a scenario than IRR.

Awaiting your response.

Regards,
Sam

Re:Please answer & explain ... 14 years 5 days ago #1698

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Sam,

Well... I normally try not to comment on the questions and explanations of other PMP Exam training companies. In this case, however, I have to agree with you that a BCR of 1.3 isn't all too bad. The real question here is, why do they think that it's "unfavorable". Maybe there is some other reasoning that we don't see.

So I have two recommendations for you:

First and foremost I'd say that you should simply shrug your shoulders and move on. It's probably not worth your time to get more into details here and you can invest your time more wisely in other studies.

Second, if you really want to know, then the best thing to do is to contact RMC directly and ask them for an explanation.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login