TOPIC: Control Charts

Control Charts 14 years 7 months ago #1387

  • Umesh Jain
  • Umesh Jain's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
A production process has been defined as part of an industrial equipment
manufacturing project.The process is intended to produce steel bolts with a
length of 20 cm.The acceptable control limits are 19.955 cm and 20.045 cm.
The measurements made at the end of the process yielded the following
results:
20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm,
19.963 cm, 19.958 cm, 19.962 cm, 19.979 cm, 19.959 cm.
What should be done?
A. The process is under control.It should not be adjusted.
B. The process should be adjusted.
C. The control limits should be adjusted.
D. The measuring equipment should be recalibrated.

Please explain the answer...

Re:Control Charts 14 years 7 months ago #1388

  • Werner Caspers
  • Werner Caspers's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
hi umesh
you should adjust the process (B)
- because the process is not under control (A), you have a series of seven values
below mean
- If control limits were set right in the 1st place, they should not be adjusted.
- measuring equipment usually get recalibrated as part of regular maintenance

kind regards Werner

Re:Control Charts 14 years 7 months ago #1389

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 619
Umesh,

To ensure that we follow proper copyright procedures here in the foreum: Please let us know where this question comes from.

Thanks.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Control Charts 14 years 7 months ago #1390

  • Umesh Jain
  • Umesh Jain's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
This question was selected from ' www.oliverlehmann.com/pmp-self-test/75-free-questions.htm ' and the answer given is 'A special cause should be investigated, the process should be adjusted'
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login