TOPIC: WBS Dictionary Vs Sequence Activities

WBS Dictionary Vs Sequence Activities 14 years 9 months ago #1312

  • Saravana Chilla
  • Saravana Chilla's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hi,

Can anyone explain the difference between WBS Dictionary Vs Sequence Activities?

WBS disctionary also has information about time, cost, resources assigned, along with more technical details of WBS. While, time, effort are planned during Duration Estimates and Schedule Activity Resources, how can WBS dictionary would have this information available.


Thanks,
Saravana

Re:WBS Dictionary Vs Sequence Activities 14 years 9 months ago #1314

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Saravana,

The most basic difference is this:

The WBS Dictionary is a document that lists more details about the work packages in the WBS. Inmportant: It contains information on a WORK PACKAGE level.

Sequence Activities is the process of organizing tasks in a logical sequence. Important: This is the sequencing of TASKS

So you see that these 2 items manage different aspects of your project - work packages in one and tasks in the other.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:WBS Dictionary Vs Sequence Activities 14 years 9 months ago #1315

  • Saravana Chilla
  • Saravana Chilla's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Sure,
(This is not related to this thread)
Why do "Create WBS" process has decomposition as a T&T, when the actual decomposition is happening at Define Activities process in Time Management. Thats some what confusing to me.

Re:WBS Dictionary Vs Sequence Activities 14 years 9 months ago #1316

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 620
Saravana,

Decomposition is just an activity. You can decompose deliverables (on a WBS) and you can decompose activites (in Time). Decomposing just means : Breaking down into smaller bits.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login