fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: CCB vs constraints

CCB vs constraints 2 years 5 months ago #29606

  • SESHACHALAM A K
  • SESHACHALAM A K's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
can someone advise what should be the BEST answer and WHY : Obviously 1 and 4 not the correct answer. but its argument between 2 and 3.

The latest change request you received does not impact the project cost. As a PM, what should be your next step?
1. Speak to your manager about the change request
2. Send the change request to the CCB
3. Evaluate the impact on other constraints
4 Go ahead and make changes.

CCB vs constraints 2 years 4 months ago #29635

  • Sameer Menda
  • Sameer Menda's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 279
  • Karma: -1
  • Thank you received: 7
As a PM, one should estimate the impact of change request on project cost, schedule and any other constraints and then document it as well. This information is used during change control meetings.

So, what should be your next step as per the question?

Answer: 3
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
The following user(s) said Thank You: Agnieszka Kwiatkowski
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login