TOPIC: Estimate At Completion Formula

Estimate At Completion Formula 2 years 8 months ago #29153

  • Nour Belkadi
  • Nour Belkadi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hello,
I need some help to understand which formula use to calculate the EAC please?
EAC = AC + (BAC – EV)
EAC = BAC / CPI
EAC = AC + [(BAC – EV) / (CPI * SPI)]
EAC = AC + Bottom-up Estimate to Complete
Thank you.

Estimate At Completion Formula 2 years 8 months ago #29155

  • Brad Pennington, PMP
  • Brad Pennington, PMP's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 44
  • Karma: 5
  • Thank you received: 6
It will depend on the information given in the problem statement. All of the formulas are looking for a slightly different answer based upon desired accuracy, stakeholder needs, etc. For what it’s worth, the one EAC problem that I saw on my exam in 2020 made it very obvious which formula to use, and I only had maybe three questions total which required the use of any formula at all. Hope this helps!
Brad Pennington, PMP
PrepCast Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login