fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Cost Reimbursable Vs Time and Material contracts

Cost Reimbursable Vs Time and Material contracts 2 years 9 months ago #29100

  • Romain Dufros
  • Romain Dufros's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello !

I have carefully read the definitions for both types of contracts in the PMBOK Guide, in the PrepCast, and even in a prep book, but the difference still baffles me.
I understand that both concepts are very similar, you pay your vendor as you go based on the time the vendor spent and the resources the vendor used.

Could you please help me clarify what is the differentiator? It's not always straightforward to choose between the 2 in exam questions !

Thanks a lot
Romain

Cost Reimbursable Vs Time and Material contracts 2 years 9 months ago #29101

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
They certainly are a bit similar in nature. I consider cost reimbursable to be used more often when the scope is uncertain. Time and material a bit more on the side where the scope is understood, but perhaps the duration is uncertain. I tend to find time and material contract terms more simple than cost reimbursable.

Just my experience though, I deal way more with time and material contracts.

Kyle
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Romain Dufros
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login