TOPIC: communication management plan update

communication management plan update 2 years 9 months ago #29011

  • Raed Almolla
  • Raed Almolla's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
if any reason led to update communication management plan such as one new stakeholder join , one stakeholder leave the project ,communication requirement of one stakeholder had been changed , so to update communication management plan as it is part of project management plan , change request will be submitted but in such a case is it required to forward it to CCB or project manager can take action and give approval directly for such change requests

communication management plan update 2 years 9 months ago #29015

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
Personally I would not require a change request form for the communications plan. I would use document version control to issue a new version with a note saying why it was updated. The kind of change you mention - a new stakeholder - doesn't impact cost/delivery/scope/timelines etc so it wouldn't warrant using the change management process. Your configuration management plan will set out what documents require change control forms and CCB approval.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login