fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project Charter always needed for both predictive and agile, right?

Project Charter always needed for both predictive and agile, right? 3 years 8 months ago #26796

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
My understanding is that a project charter is always needed. It does not matter if your project is predictive or agile . Is that correct? If an agile project does not require a formal project charter, please provide a reference.

Project Charter always needed for both predictive and agile, right? 3 years 8 months ago #26800

  • Kyle Aagenes
  • Kyle Aagenes's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Karma: 2
  • Thank you received: 3
"While the absence of a well-written Project Charter would lead to unnecessary downstream difficulties, it would not initially affect the launch of the execution process of a project. "

www.pmi.org/learning/library/agile-pmbok...anagement-scrum-6954
The following user(s) said Thank You: Sharon S, Markus Kopko

Project Charter always needed for both predictive and agile, right? 3 years 8 months ago #26854

  • Markus Kopko
  • Markus Kopko's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 45
  • Karma: 2
  • Thank you received: 7

Kyle Aagenes wrote: "While the absence of a well-written Project Charter would lead to unnecessary downstream difficulties, it would not initially affect the launch of the execution process of a project. "

www.pmi.org/learning/library/agile-pmbok...anagement-scrum-6954


Great Resource, thanks.
But, since this is from 2008, I think it should be urgently updated to reflect the evolvement since then ...
"Management is about doing the things right;
Leadership is about doing the right things!" (Peter Tucker)
The following user(s) said Thank You: Kyle Aagenes

Project Charter always needed for both predictive and agile, right? 3 years 8 months ago #26855

  • Markus Kopko
  • Markus Kopko's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 45
  • Karma: 2
  • Thank you received: 7

Sharon S wrote: My understanding is that a project charter is always needed. It does not matter if your project is predictive or agile . Is that correct? If an agile project does not require a formal project charter, please provide a reference.


You are correct, at least in terms of the PMP Exam and the "PMIs View" on Project Management.

In agile approaches the Artifact might not be called "Project Charter" but "Project Overview" or whatever, nevertheless there should be some kind of formal document that states the project vision and mission and that justifies the authorization of the project and the PM.

Regards,

Markus
"Management is about doing the things right;
Leadership is about doing the right things!" (Peter Tucker)

Project Charter always needed for both predictive and agile, right? 3 years 8 months ago #26856

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
Please provide your reference.
Last edit: by Sharon S.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login