TOPIC: Reduced team: change schedule baseline and scope or new roadmap and meetschedule

Reduced team: change schedule baseline and scope or new roadmap and meetschedule 3 years 7 months ago #26692

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
When your team gets reduced by losing people, I saw two different responses on two different questions How can I tell when to do what?

On one question the answer was to submit a C/R to change the schedule baseline and or scope since with fewer people they would not be able to finish the project on time.

Another question had the same scenario of reducing the team but the correct answer was to have the stakeholders re-do the roadmap and re prioritize features so that the team can finish on time.

How would the team finish on time if they have fewer people even if the roadmap is revised? The answer implies that by re- doing the road map, the stakeholders would be reducing the number of features. But I don't know that is really what they are saying.....

How would I know what is the right answer to pick?
Last edit: by Sharon S.

Reduced team: change schedule baseline and scope or new roadmap and meetschedule 3 years 7 months ago #26706

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hello Sharon,

Sorry, I may not have a straight answer for you, because it is hard for us to give you an explanation without the full context of the exam questions.

Two things I can advise, however:
1. When PMI is designing the exam questions, they want you to pick the best answer out of the 4 choices.
2. Pay attention to what stage the project is in. For instance, you don't need a CR if the project is still in the planning stage.
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: Sharon S

Reduced team: change schedule baseline and scope or new roadmap and meetschedule 3 years 7 months ago #26710

  • Kyle Aagenes
  • Kyle Aagenes's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Karma: 2
  • Thank you received: 3
Don't "develop schedule", "plan risk responses", and "plan procurement management" in the Planning stage produce change requests as outputs?
The following user(s) said Thank You: Sharon S
Last edit: by Kyle Aagenes.

Reduced team: change schedule baseline and scope or new roadmap and meetschedule 3 years 7 months ago #26776

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
Thank you. That makes sense.

If in execution write a C/R
On one question the answer was to submit a C/R to change the schedule baseline and or scope since with fewer people they would not be able to finish the project on time.


If in Planning re-do roadmap
Another question had the same scenario of reducing the team but the correct answer was to have the stakeholders re-do the roadmap and re prioritize features so that the team can finish on time.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login